第四日(用-5-4)橋工 凡於河道山谷街衢或他 鐵路上建設橋樑棧道假設橋水溝以便敷設 軌道者不論架構造地下構造導水工作 碎石堤岸斜陂等其橋臺橋脚支柱護墩轉動 橋樑之機器護軌洩水渠之石工與翼牆油 飾橫梁及換置橋旁道木一切維持修理費又 凡架空地下構造之維持飾新費建築新橋時 之遷毀舊橋費及防備冰水河流衝毀橋梁之 費均列入此目又橋上之發光設備費亦列入 此目

E-5-4 Bridgework–Under this head should be charged all costs for the maintenance and repair of all parts of bridges, viaducts, trestles, culverts, &c., erected to carry track over water courses, ravines, streets or other railways, both substructure and superstructure; training works, spurs and pitching connected there- with, abutments, piers, supports, draw and pier protec- tion, machinery to operate bridges, guard rails, masonry ends and wing walls for culverts, training works on the banks of rivers, the cost of painting and renewing girders and retimbering side-ways of bridges, maintaining and renewing the substructures and superstructures, the cost of removing old bridges in connection with the construction of new bridges, and the cost of works necessary to protect bridges from damage by ice, water, drift, &c. The cost of lighting bridges should also be charged to this head.

[102]

343

第五目(用-5-5)軌道 凡維持軌道之工資材料

費均列入此目照下列各分配之

第一節(用-5-5-1)工資 凡維持軌道之長班工 匠及趕班工匠之費用及更換已經損壞材 料之工費或關於維持軌道之他項工費均 列入此節

第二節 (用-5-5-2)軌枕 凡幹線支線岔道橋 梁隧道小件工廠站場船埠橋椿等之軌枕 及橋枕枕木飾新費均列入此節(特別道 义枕木不在此列)並包括查察費及維持 費在內

第一條(用-5-5-2-1)原價 凡上項送交本路

之軌枕祇將原價列入此條

第二條(用-5-5-2-2)運費 凡軌枕在本路裝

E-5-5. Track-Under this head should be charged (dis- tributed as provided below) the cost of material and labour used in maintaining track.

E-5-5-1. Labour-Under this head should be charged the cost of all regular maintenance gangs, em- ployed as well as the cost of flying gangs entirely employed on the upkeep of track; also the cost of all labour employed for the purpose of replacing damaged or worn out material, or any other work connected with the maintenance of track.

E-5-5-2. Sleepers-Under this head should be charged the cost of renewing all sleepers and bridge ties (except special crossing sleepers) in the main or branch lines, sidings, bridges, tunnels, minor workshops, station yards, wharves, piers, &c., in- cluding the cost of inspection and preservation by whatever process.

E-5-5-2-1. Cost-Under this head should be charged only the cost, as described above, of sleepers delivered to home line,

[ 103 1